There’s been several small setbacks, but work is still progressing on the new fire station. Interior rooms have been painted, the propane tanks have been buried and most of the concrete has been poured, with the remaining portions scheduled to be completed soon. The grid ceilings in the administration section will be installed this week and epoxy flooring should begin next week. HVAC components are arriving and being installed and the building is being connected to electrical service. We are in the final stretch and things seem to be coming together!